The development flow(contract case) GC01
The following is the flow of the case contracting the request and developing.
Developer (GURUGURU-MOYOU)
The preparation of development
Confirming the detail of the request and listening more
Deciding the detailed requirement
Number of letters, supporting environment, version or etc.
Making the test specification
The test specification is not enough
Fixing the parts of not enough
The test specification is okay
Making the estimate based on the test specification(price, day of deliver, and schedule of process
The estimation is not enough
Fixing the parts of not enough
The start of development work
The work of development
(The start)
Advancing the development based on the test specification
Adding necessary items in the test specification if they exist
Correcting excess or deficiency which could not be noticed at the time to make the test specification
Testing parts right then when they are completed and confirming the Implementation
At the time to confirm the progress, preparing the things which can be seen acting
Additional requests(can be responded
Adding necessary items in the test specification
Advancing the development of the additional parts
Additional requests(can not be responded
Making the reason of impossible clear, determining the handling(brought to next phase, advanced with reviewing price and day of deliver, or etc.)
Keeping it recorded in the form which can be soon confirmed later
Before deliver
(The finish of development)
Doing the total test based on the test specification by developer side, fixing any defects if they exists
Delivering temporarily(for last confirmation of the actions, the design, etc.
Detailed requests about the actions, the design, or etc.(can be responded
Adding necessary items in the test specification
Advancing the development of the additional parts
Detailed requests about the actions, the design, or etc.(can not be responded
Making the reason of impossible clear, determining the handling(brought to next phase, advanced with reviewing price and day of deliver, or etc.)
Same treatment as additional requests in developing
Keeping it recorded in the form which can be soon confirmed later
No problems about the actions, the design, and etc.
Doing the total test based on the test specification by developer side again, fixing any defects if they exists
Delivering temporarily(for last confirmation of the functions
In case there are any defects when it is tested by the client
fixing any defects and updating the temporarily delivered
In case there are no problems
Delivering formally together with the test specification
Deliver
The receipt of the delivery
With being able to confirm the payment, contacting the confirmation of payment